rp5400 and rp5430 Servers support
a maximum of two CPUs. rp5450 and rp5470 Servers support a maximum of four CPUs. The following rules govern the installation of CPUs in rp54xx
Servers: CPUs must be installed in the following
slot number order: For For rp5400 and rp5450 single CPU configurations,
a processor terminator must be installed in slot 3. The terminator is not required for rp5430 and rp5470.
 |  |  |  |  | CAUTION: Failure to install the processor terminator, where
required, can result in the server failing to pass self-test. |  |  |  |  |
Power down and unplug the
rp54xx Server.  |  |  |  |  | CAUTION: DC voltages are present when the server is connected
to AC power. Do not install or service rp54xx internal components
while DC voltage is present. Failure to observe this precaution
can result in damage to the server. |  |  |  |  |
Make the top of the server accessible for service. Loosen the captive T-15 screws that hold the top cover
in place, then grasp the strap handle, raise the cover slightly,
and pull the cover toward the front of the server to free the cover
tabs from the slots in the chassis. The air baffle will be exposed. Loosen the captive T-15 screws on the air baffle. Grasp
the two handles on the baffle, and lift the baffle remove it.  |  |  |  |  | CAUTION: Observe all electrostatic discharge (ESD) precautions
Do not touch internal components. Failure to observe ESD precautions
can cause damage to components. |  |  |  |  |
The following outlines which CPUs and processor support
modules are installed for which rp5400 and rp5450 CPU configurations.
If installing on an rp5470 proceed to the next step. | Number of CPUs | CPU Numbers to be Installed | PSM Numbers to be Installed |
|---|
| One | 0 | 0 | | Two | 0 and 3 | 0 | | Threea | 0, 1, and 3 | 0 and 1 | | Foura | 0, 1, 2, and 3 | 0 and 1 |
The following outlines which CPUs and processor support
modules are installed for which rp5470 CPU configurations. | Number of CPUs | CPU Numbers to be Installed | PSM Numbers to be Installed |
|---|
| One | 0 | 0 | | Two | 0 and 2 | 0 | | Three | 0, 1, and 2 | 0 and 1 | | Four | 0, 1, 2, and 3 | 0 and 1 |
Perform CPU Socket Cleaning Procedure detailed
in the Removal and Replacement chapter. Install processor support modules, as required. | Number of Processors Installed | Processor Support Modules Required |
|---|
| One (1) CPUs | PSM 0 | | Two (2) CPUsa | PSM 0 | | Three (3) CPUs | PSMs 0 and 1 | | Four (4) CPUs | PSMs 0 and 1 |
a. If installing a second CPU, on rp5400 or rp5450, remove
the processor terminator in slot 3. Replace the air baffle. Tighten the four captive screws
to secure the air baffle in place. Replace the top cover. Tighten the four captive screws
to secure the top cover in place. For rack configurations, insert the rp54xx Server back
into the rack. For deskside enclosure configurations, replace the deskside
enclosure cover. Plug in and power-up the rp54xx Server. Use the BCH command in pr to verify that the system recognizes the processors that
you have just added.
|