 |
» |
|
|
 |
This section provides electrical specifications for Superdomes. Grounding |  |
The site building shall provide a safety ground/protective
earth for each AC service entrance to all Superdome cabinets. This equipment is CLASS 1 and requires full implementation
of the grounding scheme to all equipment connections. Failure to
attach Protective Earth results in loss of regulatory compliance
and creates a possible safety hazard. Circuit
Breaker |  |
Each Superdome cabinet using a 3-phase, 4-wire input requires
dedicated circuit breaker to support the Marked Electrical current
of 44A per phase. The facility electrician and local service codes
will determine proper circuit breaker selection. Each Superdome cabinet using a 3-phase 5-wire input requires
a dedicated circuit breaker to support the Marked Electrical current
of 24A per phase. The facility electrician and local service codes
will determine proper circuit breaker selection.  |  |  |  |  | NOTE: See Table E-1 “Typical Superdome Configurations” for
systems that are configured with less than a full compliment of cell
boards, memory, and I/O modules.When using the minimum sized breaker, always choose
circuit breakers with the maximum allowed trip delay to avoid nuisance
tripping.As of March, 2002, PDCA Options 4 and 5 are obsolete. |  |  |  |  |
Detailed site power information is required to configure the
system correctly and prevent delays in system installation. Collect
the following information from the customer site electrician before
selecting the appropriate PDCA. Type of source
available 4-wire_____ 5-wire_____ Source voltage phase-to-phase
_____ Vac Source voltage phase-to-neutral
_____Vac
Using the above information, determine the appropriate power
option from Table 1-6 “Available Power Options”. Select the source
type that matches the customer source. Within the matching Source
Type selection, select the matching voltage range to the customer's
source voltage. Select the appropriate PDCA. The customer must either
provide the correct mating in-line connector or order one from HP.
See Table 1-8 “Options 006 and 007 Specifics” for details.
Example 1-1 The customer
has a 3-phase source with a Source Voltage of 208 VAC measured phase-to-phase
indicating that a 4-wire PDCA is required. Example 1-2 The customer
has a 3-phase source with a Source Voltage of 220 VAC measured phase-to-neutral
indicating that a 5-wire PDCA is required. Example 1-3 The customer
has a 3-phase source with a Source Voltage of 230 VAC measured phase-to-phase
indicating that a 4-wire PDCA is required. Example 1-4 The customer
has a 3-phase source with a source voltage of 415 VAC measure phase-to-phase
and a measured phase-to-neutral source voltage of 240 VAC, indicating
a 5-wire PDCA is required. Input Power
Options |  |
Table 1-6 “Available Power Options” describes the available
power options: Table 1-6 Available Power Options | PDCA Product Number | Source Type | Source Voltage (nominal) | PDCA Required | Input Current Per Phase 200-240 VAC | In-line Connector Required |
|---|
A5800A Option 001[1] | 3-phase | Voltage range 200-240 VAC, phase-to-neutral, 50/60
Hz (EUR typical)[2] | 5-wire | 24A Maximum per phase | None required. Electrician must hard wire
power to the PDCA[3] | A5800A Option 002a | 3-phase | Voltage range 200-240 VAC, phase-to-phase, 50/60
Hz (US typical) | 4-wire | 44A Maximum per phase | None required. Electrician must hard-wire power
to the PDCAc | A5800A Option 004[4] | 3-phase | Voltage range 200-240 VAC, phase-to-phase, 50/60
Hz (US typical) | 4-wire | 44A Maximum per phase | In-line connector and plug provided with a 2.5-meter
power cable. Electrician must hard-wire in-line connector to 100A
site power.c,[5] | A5800A Option 005d | 3-phase | Voltage range 200-240 VAC, phase-to-neutral, 50/60
Hz (EUR typical) | 5-wire | 24A Maximum per phase | In-line connector and plug provided with
a 2.5-meter power cable. Electrician must hard-wire in-line connector
to 60/63A site power.c,e,[6] | A5800A Option 006[7] | 3-phase | Voltage range 200-240 VAC, phase-to-phase, 50/60
Hz | 4-wire | 44A Maximum per phase | 2.5meter UL power cord and UL approved plug
provided. The customer must provide the mating in-line connector
or purchase quantity one A6440A opt 401 to receive a mating inline connector.
An electrician must hard wire the in-line connector to 60A/63A site
power.c,f,[8] | A5800A Option 007[9] | 3-phase | Voltage range 200-240 VAC, phase-to-neutral, 50/60
Hz | 5-wire | 24A Maximum per phase | 2.5meter <HAR> power
cord and VDE approved plug provided. The customer must provide the
mating in-line connector or purchase Quantity 1 A6440A opt 501 to
receive a mating in line connector. An electrician must hard wire
the in-line connector to 30A/32A site power.c,h,[10] |
Table 1-7 Option 004 and 005 Specifics[1] PDCA Product Number | Attached Power Cord | Attached Plug | Connector Provided |
|---|
A5800A Option 004 | OLFLEX 190 (PN 600404) is a 2.5 meter
multi conductor, 600 volt, 90 degree C, UL and CSA approved, oil
resistant flexible cable. (100 A capacity) | Mennekes ME 4100P9 (100
A capacity) | Mennekes ME 4100C9 (100
A capacity) | A5800A Option 005 | H07RN-F (OLFLEX PN 1600111) is a 2.5
meter heavy duty neoprene jacketed harmonized European flexible cable.
(63 A capacity) | Mennekes ME 563P6-1235 (63
A capacity) | Mennekes ME 563C6-1245 (63
A capacity) |
Table 1-8 Options 006 and 007 Specifics | | | Customer-Provided Part |
|---|
PDCA Product Number | Attached Power Cord | Attached Plug | In-Line Connector | Panel-Mount Receptacle |
|---|
A5800A Option 006 | OLFLEX 190 (PN 600804), four-conductor, 6-AWG (16-mm2),
600-Volt, 60-Amp, 90-degree C, UL, and CSA approved, conforms to
CE directives GN/YW ground wire. | Mennekes ME 460P9 3-phase,
4-wire, 60-amp, 250-volt, UL approved. color blue, IEC 309-1, IEC
309-1, grounded at 3:00 o'clock. | Mennekes ME 460C9 3-phase,
4-wire, 60-amp, 250-volt, UL approved. color blue, IEC 309-1, IEC
309-1, grounded at 9:00 o'clock.[1] | Mennekes ME 460R9 3-phase,
4-wire, 60-amp, 250-volt, UL approved. color blue, IEC 309-1, IEC
309-1, grounded at 9:00 o'clock.[2] | A5800A Option 007 | Five conductors, 10-AWG (6-mm2),
450/475-volt, 32-amp, <HAR> European wire cordage,
GN/YW ground wire. | Mennekes ME 532P6-14 3-phase,
5-wire, 32-amp, 450/475-volt, VDE certified, color red, IEC
309-1, IEC 309-2, ground at 6:00 o'clock. | Mennekes ME 532C6-16 3-phase,
5-wire, 32-amp, 450/475-volt, VDE certified, color red, IEC
309-1, IEC 309-2, ground at 6:00 o'clock.[3] | Mennekes ME532R6-1276 3-phase,
5-wire, 32-amp, 450/475-volt, VDE certified, color red, IEC
309-1, IEC 309-2, ground at 6:00 o'clock.b |
 |  |  |  |  | NOTE: A qualified electrician must wire the PDCA in-line connector
to site power using copper wire and in compliance with all local
codes. |  |  |  |  |
Each branch circuit used within a Superdome Complex
must be connected together to form a common ground.
When only one PDCA is to be installed in a Superdome, it must
be installed as PDCA 0. Refer to Figure 1-5 “PDCA Locations” for PDCA 0 location.  |  |  |  |  | WARNING! Do not install a PDCA that does not have one of the
following set of labels attached.  |  |  |  |  |
Power Cords |  |
This section discusses the different possibilities for Superdome
PDCA power cords. Some installations may either require or desire that the Superdome(s)
be hardwired in lieu of using the standard plugs and connectors
provided. In these cases, it is necessary to remove the installed
power cable from the PDCA. The following procedures are used to
remove and replace the existing power cable. To remove the existing cable from the PDCA, begin be removing
the five T-10 Torx screws detailed in Figure 1-9 “PDCA Cable Access (5-Wire Unit Shown)”. Then remove the bottom panel of the PDCA.
Retain the panel and screws for future use.  |  |  |  |  | NOTE: These procedures may be used for early deliveries consisting
of either option 1 or option 2 as well as those later systems delivered
with PDCA cables attached. |  |  |  |  |
Select the proper cable using the following criteria. Each Superdome
cabinet using a 3-phase, 4-wire input is required to have a four-conductor
cable. The four-conductor cable selected by the facility electrician
shall be in accordance with local electrical codes to support the
selected circuit breaker for the maximum Product Label current of
44A per phase. The facility electrician and local electrical codes
will determine proper power cord selection dependent upon desired application
such as rigid conduit, flexible conduit, or cable bundle. Observe
derating factors for multiple wires per cable. Each Superdome cabinet using
a 3-phase 5-wire input is required to have a five-conductor cable.
The five-conductor cable selected by the facility electrician shall
be in accordance with local electrical codes to support the selected
circuit breaker for the maximum Product Label current of 24A per
phase. The facility electrician and local electrical codes will
determine proper power cord selection dependent upon desired application
such as rigid conduit, flexible conduit, or cable bundle. Observe
derating factors for multiple wires per cable.
Prepare the new cable
as shown in Figure 1-11 “Cable Preparation Detail”. Using the cable retaining hardware
saved from the cable removal, route the new cable into the PDCA. Route the cable into the PDCA
terminal lugs and secure in position by tightening the lugs. Using the hardware that was retained
during the cable removal, attach the green and yellow ground cable. Using the five screws retained
from the removal procedure, replace the bottom panel on the PDCA. Refer
to Figure 1-9 “PDCA Cable Access (5-Wire Unit Shown)” for panel
installation details. To verify the proper wiring to a 4-wire PDCA, use a
DVM to measure the voltage at the test points. Voltage should read
200 - 240 Vac phase-to-phase as measured between the test points
as follows: L1 to L2, L2 to L3, L1 to L3.  |  |  |  |  | IMPORTANT: In some electrical distributions around the world,
it is possible to measure 415 VAC phase-to-phase. Ensure that your
DVM is capable of measuring AC voltages of at least 500VAC. A number
of 5-wire power distribution systems may have phase-to-phase voltages
in excess of 400VAC. Many hand-held volt meters are limited to 300VAC. |  |  |  |  |
To verify the proper wiring to a 5-wire PDCA, use a DVM to
measure the voltage at the test points. Voltage should read 200-240VAC
phase-to-neutral, as measured between the test points as follows: L1
to N, L2 to N, L3 to N.
 |  |  |  |  | NOTE: Dimensions shown are for a cable strain relief without
an extension nipple. If an extension nipple is used, then the cable
jacket must removed accordingly. Figure 1-11 “Cable Preparation Detail” shows a
4-wire cable for illustrative purposes only. 5-wire cable is dimensionally identical
regarding insulation and jacket removal. The only exception is the
number of conductors. |  |  |  |  |
System
Power Requirements |  |
Table 1-9 “Power Requirements (without Support Management Station)” and Table 1-10 “Component Power Requirements (without Support
Management Station)” list the AC power requirements for
a Superdome. These tables provide information to help determine
the amount of AC power needed for your computer room. Table 1-9 Power Requirements (without Support Management Station) | Requirements | Value | Comments |
|---|
| Nominal input voltage | 200/208/220/230/240 VAC | | | Input voltage range (minimum - maximum) | 200 - 240 VAC | Autoselecting (measured at input terminals) | | Frequency | 50/60 Hz | | | Number of phases | 3 | | | Maximum inrush current | 90 A peak | | | Product Label maximum current, 3-phase, 4-wire | 44 A max | Per phase at 200-240VAC | | Product Label maximum current, 3-phase, 5-wire | 24 A max | Per phase at 200-240VAC | | Power factor correction | 0.95 minimum | | | Ground leakage current (mA) | > 3.5 ma | See WARNING below. |
 |  |  |  |  | WARNING! Beware of shock hazard. When connecting or removing
input power wiring, always connect the ground wire first and disconnect
the ground wire last. |  |  |  |  |
I/O Expansion
Cabinet Power Requirements |  |
The I/O expansion cabinet requires a single phase 200-240VAC
input. Table 1-11 “I/O Expansion Cabinet Power Requirements
(without Support Management Station)” lists the AC power requirements
for the I/O expansion cabinet.  |  |  |  |  | NOTE: The IOX accommodates two AC inputs for redundancy |  |  |  |  |
Table 1-11 I/O Expansion Cabinet Power Requirements
(without Support Management Station) | Requirements | Value |
|---|
| Nominal input voltage | 200-240 VAC | | Input voltage range (minimum-maximum) | 200-240 VAC | | Frequency range (minimum-maximum) | 50/60 Hz | | Number of phases | 1 | | Marked Electrical input current | 16A max | | Maximum inrush current | 60 A peak | | Power factor correction | 0.95 minimum |
Table 1-12 I/O Expansion Cabinet Component Power Requirements Power Required (50 - 60 Hz) | VA |
|---|
Fully configured cabinet | 3200 | I/O cardcage | 500 | | ICE | 600 |
I/O Expansion
Cabinet Power Cords |  |
Table 1-13 “I/O Expansion Cabinet AC Power Cords” lists the power
cords for the I/O expansion cabinet. Table 1-13 I/O Expansion Cabinet AC Power Cords | Part Number A5499AZ | Where Used | Connector Type |
|---|
| -001 | North America | L6-20 | | -002 | International | IEC 309 |
Peripheral
Cabinet Power Requirements |  |
There is a high probability that an existing peripheral cabinet
may be incorporated into this system. Ensure that adequate power
is available for this cabinet and the associated peripherals. Support
Management Station Power Requirements |  |
Refer to the applicable documentation for the SMS power requirements.
|