The following schedule lists the sequence of events for a
typical system installation:
60 days before installation
Floor plan design completed and mailed
to Hewlett-Packard
30 days before installation
Primary power and air conditioning
installation completed
Telephone and data cables installed
Fire protection equipment installed
Major facility changes completed
Special delivery requirements defined
Site inspection survey completed
Delivery survey completed
Signed copy of the site inspection and delivery
survey mailed to Hewlett-Packard
Site inspection and pre-delivery coordination meeting
arranged with a Hewlett-Packard representative to review the inspection
checklist and arrange an installation schedule.
7 days before installation
Final check made with a Hewlett-Packard
customer engineer to resolve any last-minute problems