Adding additional capacity to an existing system requires
careful consideration and planning. A Solution Implementation Plan
(SIP) should be developed before visiting the customer site.
Figure 3-7 “PDCA
Locations ” shows a cabinet
with both PDCAs installed. PDCA 0 is the first PDCA. PDCA 1 is the
position of the additional PDCA.
Adding
the Option 6 or Option 7 PDCAs |
 |
To add the Option 6 or Option 7 PDCA:
Shut down the server.
Power off the AC supply to the server.
Remove the power plug from the power source.
Install the new PDCA into the server.
Run the power cord down through the
appropriate opening in the floor tile.
Partially insert the PDCA into its slot.
Slip the L bracket under the power cord on the rear
of the PDCA.
While holding the L bracket in place, insert the
PDCA completely into the cabinet and secure the L bracket with one
screw.
Using a T20 Torx driver, attach the four screws
that hold the PDCA in place.
Plug the power cord into the AC power source.
Power on the AC supply to the server.
Power on and boot up the server.